Microsoft Project 2010 (Number of days late for a project) - Microsoft Community


hello,

how can show number of days late in microsoft project 2010?  have late status indicator field , status indicator field, know number of days late on different tasks.  job start 9/27/16 , still has not started , want show number of days late each task, if can me this, great-full.

msm_1718 --

assuming saved baseline project, click view tab display view ribbon.  in data section of view ribbon, click table pick list , select variance table.  drag split bar right can see of columns in variance table.  column called finish variance column show slippage data seek.  hope helps.