hello,
how can show number of days late in microsoft project 2010? have late status indicator field , status indicator field, know number of days late on different tasks. job start 9/27/16 , still has not started , want show number of days late each task, if can me this, great-full.
msm_1718 --
assuming saved baseline project, click view tab display view ribbon. in data section of view ribbon, click table pick list , select variance table. drag split bar right can see of columns in variance table. column called finish variance column show slippage data seek. hope helps.