hello,
i trying create formula off of flag field return finish date. if flag field yes task finish date needs displayed. if flag field no needs display na. me put formula together?
the flag field called "deliverable flag"
thanks
krfoundations --
assuming using flag1 field mark deliverables, formula follows:
iif([flag1] ,[finish],projdatevalue("na"))
if not using flag1, substitute name of flag field in preceding formula. if marking summary tasks deliverables, sure select "use formula" option custom field in middle of dialog. hope helps.